Location
Sligo
Status
Completed
Investment
€16 million

Benefits

  • Increased treatment capacity of the plant to meet current needs of the town and allow for future growth
  • Improved water quality of nearby coastal areas, protecting bathing areas and the environment from pollution
  • Ensure wastewater is treated and discharged in compliance with EU regulations

What was involved?

  • Increased capacity of the existing wastewater treatment plant from 1,500 population equivalent (PE) to 3,700 PE.
  • New inlet works, storm water holding tank, secondary biological treatment, settlement tanks, control building and a sludge thickening facility.
  • Upgraded the existing Caravan Park Pumping Station.