Location
Monaghan
Status
Planned
Investment
€1.1 million

Benefits

  • Upgrade existing infrastructure at the plants and provide new elements where defects identified
  • Improve the performance of the wastewater treatment process
  • Prolong the operational life of the existing plant
  • Reduce the risk of storm water flooding
  • Ensure compliance with Urban Wastewater Treatment Regulations 2001

Steps

  • Install a new bypass screen, storm water holding tank and pumps and provide a roof cover for the sludge treatment facility at the Ballybay Plant
  • Install a new bypass screen, an underground storm water tank and pumps and effluent pumping station at the Smithborough Plant
  • Install a new inlet works with grit removal, Sludge Dry Red Beds with pumping station and associated pipework and effluent pumping station at the Clones Plant
  • Works will be carried out within the footprint of the plants therefore minimising disruption to residents and businesses in the surrounding area