Location
Cork
Status
Completed
Investment
€12.3 million
The upgraded plant will ensure all effluent is treated to a high standard that is compliant with EPA standards.

Benefits

  • Ensures treated effluent complies with EPA standards
  • Increased wastewater treatment capacity
  • Resolved odour and noise issues
  • Allowed for future growth in population and economic development

Steps

  • Construction of a wastewater treatment plant for an increased population equivalent of 30,000 
  • Provision for phased extensions to the plant in the future for 45,000 and 60,000 Population Equivalent (PE)
  • Operation of the existing wastewater treatment works, pumping stations and rising mains in Carrigtohill