Skip to main content
Video file

Water Supply Project Eastern and Midlands Region

This project has capacity to address supply water needs for up to 50% of the State’s population.


This project has capacity to address supply water needs for up to 50% of the State’s population.

Planning permission has now been lodged to An Coimisiún Pleanála. Planning documents can be viewed at www.watersupplyproject.ie

Community Engagement

Uisce Éireann have appointed a Community Liaison Officer (CLO) for the Water Supply Project Eastern and Midlands Region. The CLO is available to meet with members of the community, including at a number of drop-in information clinics over the coming months.

Planned Community Engagement Clinics: Details of future events will be updated below.

If you wish to speak with the Community Liaison Officer outside of these times, please contact the project team by emailing watersupply@water.ie.

Planned Community Engagement Clinics

DateTimeLocationClinic venue
03 February 202611am - 1pmCo. KildareThe Mill Celbridge Community Centre, Co. Kildare W23 P6P5
03 February 20265pm - 7pmCo. OffalyKilleigh Community Centre, Co. Offaly R35 V446
12 February 202611am - 1pmCo. TipperaryNenagh Arts Centre, Co. Tipperary E45 CD52
12 February 20265pm - 7pmCo. ClareBallina Killaloe Family Resource Centre, Co. Clare V94 W7X6
12 March 202611am - 1pmCo. KildareStraffan Community Centre, Co. Kildare W23 V294
12 March 20265pm - 7pmCo. OffalyKilcormac Community Hall, Co. Offaly R42 X894
19 March 202611am - 1pmCo. LimerickACM Community Centre Castleconnell, Co. Limerick V94 FA0D
19 March 20265pm - 7pmCo. TipperaryThomas McDonagh Museum Cloughjordan, Co. Tipperary E53 EV29
09 April 202611am - 1pmCo. KildareThe Mill Celbridge Community Centre, Co. Kildare W23 P6P5
09 April 20265pm - 7pmCo. OffalyKilleigh Community Centre, Co. Offaly R35 V446
16 April 202611am - 1pmCo. TipperaryNenagh Arts Centre, Co. Tipperary E45 CD52
16 April 20265pm - 7pmCo. ClareBallina Killaloe Family Resource Centre, Co. Clare V94 W7X6

Project overview

Our purpose is to deliver transformative water services that enable communities to thrive. For the Eastern and Midlands Region, rising to this challenge requires a new water source.

Today, we have just one source to supply 85% of the water for the Greater Dublin Area – the River Liffey. This dependence on the Liffey (and the two main treatment plants of Ballymore Eustace and Leixlip) results in a serious vulnerability to risks such as prolonged drought and/or contamination. Furthermore, economic growth, population growth including the demand for housing and the impact of climate change means our forecasts show that the region will need 34% more water by 2044 than is available today. This combination of a growing water supply deficit and lack of supply resilience is not sustainable-we need a new source of water.

The solution is the Water Supply Project Eastern and Midlands Region. A critical national infrastructure project, it will have capacity to support water supply needs for up to 50% of our population. It will bring treated water from the Parteen Basin to Peamount in Dublin with the capacity for offtakes along the route in Tipperary, Offaly and Westmeath. It will also enable supplies serving Dublin to be redirected back locally in Carlow, Wicklow, Meath and Louth.

Status

The Water Supply Project has approval in principle under the Government’s Infrastructure Guidelines. In December 2025, We have submitted a planning application to An Coimisiún Pleanála for the Water Supply Project Eastern and Midlands Region complete with an Environmental Impact Assessment Report (EIAR) and Natura Impact Statement (NIS). The planning application can be viewed and downloaded from here watersupplyproject.ie

Location
Eastern and Midlands Region
Status
Planned
Type
Water

Water Supply Project in 2025

To find out more, click below for a short 3 minute video.

Why do we need the Water Supply Project?

Securing a water supply for up to half of Ireland's population

Icon

The River Liffey supplies 85% of the water requirements for 1.7 million people in Dublin, Meath, Kildare and Wicklow.

Icon

By depending on one source, there is no alternative if there is a contamination or weather event.

Icon

Population growth, economic growth and climate change means 34% more water will be needed by 2044.

Icon

Leakage reduction is part of the solution. We have a target of achieving Sustainable Economic Levels of Leakage by 2034.

Icon

A new source is needed to avoid restrictions and large-scale water outages. It will support economic growth and housing in the region.

Icon

This new source will provide resilience in the water system and help us to meet the challenge of climate change.

The proposed pipeline route - Water Supply Project

The Project

The proposed Water Supply Project Eastern and Midlands Region will abstract a maximum of 2% of the average flow of the River Shannon at Parteen Basin. The project is in line with the National Water Resources Plan (Framework Plan) and the Regional Water Resources Plan for the Eastern and Midlands Region. The Project will;

  • Abstraction of water from the lower River Shannon at Parteen Basin in Co. Tipperary, downstream of Lough Derg
  • Treatment of  the abstracted water at Birdhill, Co. Tipperary
  • Pipe the treated water through Tipperary, Offaly and Kildare to a termination point reservoir at Peamount in County Dublin
  • Connect into the Greater Dublin Area water supply network, with capacity to provide water to communities along the route.

WSP Map

Eastern and Midlands regional in depth Water Supply Project Map

Project Benefits

Icon

A new secure, resilient water supply for the Greater Dublin Area will support population growth, economic growth and housing.

Icon

The first ever water spine across Ireland, it will have capacity to supply communities along the route in Tipperary, Offaly and Westmeath.

Icon

A new source means we can redirect water currently serving Dublin back to communities in Louth, Meath, Kildare, Wicklow and Carlow.

Icon

The Water Supply Project enables resilience through climate adaption with more sustainable water supplies.

Icon

It will improve water services for local communities, addressing needs across 36 water resource zones.

Icon

The new source reduces dependence on the Liffey, better protecting us from drought and climate change.

Landowner Information

A landowner handbook is available to provide landowners with specific information including an overview of the proposed project, as well as detailed information on construction and post construction phases.

All landowners along the proposed project route have been assigned a dedicated Landowner Liaison Officer, who have been advising landowners on the progress of route development and technical design, as well as arranging access for environmental and ground investigation surveys. The Landowner Liaison Officers will continue to provide landowners with a dedicated point of contact throughout the planning, construction and reinstatement phases. 

Contact details have been shared with all landowners, however please email mpwayleaves@water.ie should you need any further information.

Next Steps

Icon

The Water Supply Project has approval in principle under the Government’s Infrastructure Guidelines.

Icon

It will now proceed to planning. Uisce Eireann will submit a Strategic Infrastructure Development application to An Bord Pleanála.

Icon

Subject to planning approval, construction will take 4-5 years.