Tullow Water Mains Replacement

Uisce Éireann has replaced aged water mains in Tullow Town Centre in order to provide a more reliable water supply, reduce high levels of leakage and improve water quality.

Location
Carlow
Status
Completed
Type
Leakage reduction

The works involved the replacement of over 2.1km of aged cast iron water mains with new modern pipes. The programme which replaced the water mains in Tullow Town Centre commenced in February 2025.

These works were being carried out as part of Uisce Éireann’s National Leakage Reduction Programme.

The section of works took place along Church Street, Bridge Street, Market Square, Mill Street, Bishop Street, Old Chapel Lane, John Street, The Course/ Crosskeys and Mullawn.

The works also involved laying new water service connections from the public water main in the road to customers’ property boundaries and connecting it to the customers’ water supply. 

The works were carried out on behalf of Uisce Éireann by Shareridge and were completed by November 2025.

To minimise disruption, a phased approach with areas of works limited to short sections were adopted for delivery of this project. 

The phases to facilitate works were as follows, with works commencing in Phase 1;

 

 

 

Phase 1Mill Street LowerMarch 2 weeksRoad closure
Phase 1Mill Street UpperMarch /April2 weeksRoad closure
Phase 2Church Street night works only April 2 weeksStop and go traffic management 
Phase 2The Course/Crosskeys April2 weeksStop and go traffic management
Phase 2Church Street – night works only  April/May3 weeksStop and go traffic management
Phase 2Old Chapel LaneMay/June2 weeksRoad closure
Phase 2Bishops StreetJune 2 weeksRoad closure
Phase 3John’s StreetJune /July2 weeksRoad closure
Phase 3Course/Crosskeys continuing onto Chapel Lane, Mill Street and Mullawn July2 weeksStop and go traffic management
Tullow Town Centre - Leakage Reduction Works Project Map

Tullow Town Centre - Leakage Reduction Works Project Map

What are the benefits of the works?

The benefits of these leakage reduction works include:

  • Reliable Water Supply – Replacement of problematic water mains and service connections will reduce the instances of bursts and interruptions to the water supply reducing disruption for homes and businesses in the area.
  • Reduced Leaks – Replacement of problematic water mains and service connections will eliminate existing leaks and reduce the amount of clean drinking water lost into the ground. 
  • Improved Water Quality – Removing existing old cast iron and lead from the public water network and replacing them with new pipes will reduce the risk of contamination. 
  • Improved Operation and Maintenance – These works will deliver efficiencies including cost savings by providing improved water network operation that will require less maintenance in the future.