Gowran Regional Water Supply Scheme

Water Supply Project

Uisce Éireann is progressing works to deliver a major upgrade to the Gowran Regional Water Supply.

Uisce Éireann, is progressing works on the Gowran Regional Water Supply Scheme to improve the security of water supply across Gowran, Goresbridge and Paulstown. This project represents a significant investment which will benefit over 1,200 customers.

The project includes the construction of a new water treatment plant, treated water storage tanks, rising mains and development of two abstraction boreholes to supplement existing supply arrangements. This project will also improve the quality and security of water supply for the area and provide additional capacity for connections to the scheme.

David Walsh Civil Engineering Ltd., is delivering the works on behalf of Uisce Éireann.

Location
Kilkenny
Status
In progress
Type
Water
LRP workers

What are the benefits of this project?

  • Ensure a safe, secure and reliable water supply to Gowran, Goresbridge and Paulstown.
  • Ensuring compliance with National and EU drinking water regulations.
  • Provide additional capacity to enable rationalisation of temporary treatment plants and further additional capacity to sustain future growth and development in Gowran and surrounding areas.

What are we delivering as part of this project?

  • Construction of a brand-new water treatment plant (WTP).
  • Development of new groundwater abstraction boreholes.
  • Construction of new raw water rising mains between boreholes and the new WTP.
  • Construction of two new treated water storage tanks within the new WTP site.
  • Construction of a treated water raising main between the new WTP and the existing Butlersgrove Water Tower.

What progress have we made?

  • New water treatment plant (WTP) is erected and currently being fitted out.
  • Construction of treated water storage tanks is almost complete.
  • Construction of new raw water rising mains between boreholes and the new WTP is complete.
  • Construction of a water main between the new WTP and the existing Butlersgrove Water Tower and works at Butlersgrove reservoir is complete.

We’re on track to complete this project by the end of 2025.

Uisce Éireann will endeavour to keep all stakeholders, businesses and residents informed as this essential water supply scheme progresses.