Weekly Updates
Traffic Management and Diversion Routes
Ward and Burke Construction Ltd. has a full time Community Liaison Officer on the contract who is available to address and queries or concerns in relation to the works.
Contact details: Eimear O'Brien 086 1036300.
Details of upcoming works:
Location |
Start Date |
Duration |
Planned Works |
Traffic Management |
---|---|---|---|---|
Mill Road to Seaview Avenue Link Road |
Friday 31 March 2023 | N/A | 2 Flow Traffic Resumes outside Bridgewater Shopping Centre and Traffic Lights removed from Seaview Avenue Junction |
Link Road will be closed |
South Quay (Harbour Rd Junction) |
Monday 27 March 2023 | 5 Months | Manhole construction, pipelaying & associated works | Road closure at Harbour Rd/South Quay Junction (No left turn from Harbour Rd onto South Quay) Single lane in place, west of Harbour Road, and traffic will be controlled east of the junction and along Harbour Road itself using traffic lights |
North Quay Road |
9 January 2023 | 12 Weeks | Manhole Conversions & Pipelaying |
A single lane closure will be in place on North Quay Road, with diversions in place via Seaview Avenue and the Link Road. – One way Traffic System in Place outside Bridgewater Shopping Centre |
Mill Road to Seaview Avenue Link Road |
9th Jan 2023 |
12 Weeks |
Manhole Conversions on North Quay outside Bridgewater Shopping Centre | Link Road will be reopened. A temporary traffic light system will be in place at the junction of Seaview Avenue and Ferrybank. Minor increased levels of construction vehicles |
South Quay (South Quay/ Harbour Rd Junction to Car Parking Spaces on South Quay Harbour) |
27 March 2023 |
8 Weeks |
Manhole Construction, pipelaying and associated works |
Road closure at Harbour Rd/South Quay Junction (No left turn from Harbour Rd onto South Quay) Single lane in place, west of Harbour Road, and traffic will be controlled east of the junction and along Harbour Road itself using traffic lights. No exit onto Harbour Rd from Rockview Terrace. |
South Quay – (South Green Junction to Bridge Junction) |
7 November 2022 |
On Hold |
Sheet Piling to assist with Wicklow County Council’s Flood Relief Scheme |
Single Lane Closure between South Quay Junction and Harbour Road |
Riverwalk (Arklow Bridge to Bandstand Car Park) |
17 October 2022 |
7 months |
Trial holes, service diversions, pipelaying works |
Temporary & intermittent closure of one traffic lane & suspension of some car parking spaces |
Riverwalk and Alps (Bandstand Car Park to Alps) |
26 September 2022 | 9 months | Trial holes, service diversions, pipelaying, construction of tanks, construction of retaining wall. |
Closure of riverwalk between Bandstand Car Park & Alps. No access to Riverwalk from the Coomie |
Arklow Bridge (South) | 5 September 2022 | 24 months | Bridge strengthening works & pipelaying |
Site access to river will be created opposite Asian Harvest and on the River Walk |
North Quay and Mill Road |
4 Jan 2022 |
15 Months |
Tunnel Shaft Complete – connection to be completed |
Road Closure from the T-Junction at The Lighthouse Apartments, Arklow Marina Village to the T-junction at North Quay Mill Road (Local Access Maintained) |
North Pier | 16 May 2022 | 24 months | Stockpile Rock Armour for Revetment Works |
North Pier Closure (No access beyond Wastewater Treatment Plant Site Entrance) Same as above |
Ferrybank Roundabout Structure 37 | 2 August 2022 |
12 months |
Manhole construction, pipelaying & associated works | N/A |
Old Wall Board Plant (New Wastewater treatment plant Site) |
27 Sept 2021 |
3 years |
Construction of the Wastewater Treatment Plant |
Increased levels of construction vehicles |