Location
Clane
Status
In Progress
Investment
€38 million

What is happening in Clane?

Irish Water is working in partnership with Kildare County Council to upgrade and replace the sewers in several locations in Clane. To minimise disruption, the work will be completed in phases and traffic management will be in place. Works in Clane include:

  • Installation of over 500m of new gravity sewer from the L1023 Ballinagappa Road to the R403 and along Central Park.
  • Installation of approximately 400m of new gravity sewer on the Prosperous Road.
  • Installation of approximately 3km of new rising main in the R403 from Clane to Sallins.
  • Diversion routes will be clearly signposted, as agreed with Kildare County Council and An Garda Síochána. Emergency Access and restricted Local Access will be maintained, including access to local businesses. 

The following temporary road closures will be in place to facilitate installation of key pipework as part of the project. All roads will be reopened early in the event that works are completed ahead of time, where possible. Diversion routes will be clearly signposted, as agreed with Kildare County Council and An Garda Síochána. Diversion dates may change slightly, depending on the progression of the works. Any changes in dates will be notified to relevant stakeholders ahead of time. Emergency Access and restricted Local Access will be maintained, including access to all businesses in the impacted areas. Out of hours emergency contact number is 086 3890092. Emergency Services will be notified also.

Two bus stops on the R403 (next to and opposite Circle K, Clane Road, Abbeyland) will be closed for the duration of the works. We apologise for any inconvenience this may cause.

Diversion Routes

1. Outer Diversion Route for Regional Traffic for all phases of works (23 March to 30 April, 2020)

2. Inner Diversion Route for Local Access for phases 1 and 2 (23 March to 4 April, 2020)

3. Inner Diversion Route for Local Access for phase 3 (6 April to 10 April, 2020)

4. Inner Diversion Route for Local Access for phase 4 (11 April to 18 April, 2020)

5. Inner Diversion Route for Local Access for phase 5 (20 April to 30 April, 2020)

What is involved?

  • Lay over 18km of new gravity sewers and rising mains to reinforce and improve the existing wastewater sewer network.
  • Upgrade wastewater pumping stations at Sallins, Clane and Monread (Naas).
  • Build additional storm water storage tanks at all three pumping stations
  • Wastewater will continue to be pumped to Osberstown for treatment.

Why are these works necessary?

  • The existing wastewater network is no longer fit for purpose. The system doesn’t have sufficient capacity to move wastewater to the treatment plant during storms, and some of the pipes are old and ready for replacement.
  • There have been storm water overflows at a number of locations, which does not comply with European legislation or Environmental Protection Agency requirements.
  • To increase the capacity of the network we are upgrading three pumping stations and upgrading and replacing existing sewers to ensure they are large enough and in good condition. We will include stormwater storage at each of the pumping stations which will improve resilience during storms.

Benefits

  • Improved water quality in the river Liffey and tributaries, in compliance with national and EU legislation.
  • Improved energy efficiency at all three pumping stations.
  • The sewer network will have increased capacity to support future growth in the area.

View more projects

Back to the top