Read what to do.

New Wastewater Treatment Plant to benefit Baile Bhuirne and Baile Mhic Íre

17 November 2021

Uisce Éireann has completed works on a new wastewater treatment plant that will serve the people of Baile Bhuirne (Ballyvourney) and Baile Mhic Íre (Ballymakeera), protect the local environment, and support growth and development in the area for years to come.

Both areas were previously served by overloaded and outdated wastewater treatment infrastructure and therefore a new wastewater treatment plant and network upgrades were required. The new treatment plant ensures an end to the discharge of poorly treated waste and will improve the water quality in the receiving waters.

This project, carried out in partnership with Cork County Council, brings immense benefits to both communities by ensuring that there is adequate treatment of wastewater, for now, and into the future, as well as protecting public health and safeguarding the environment. The project also ensures compliance with the European regulatory standards.

Uisce Éireann is investing €27 million in mid-West Cork area, part of which was used to carry out this project. The project upgraded several aspects of wastewater treatment and enhances local amenities. The new infrastructure is sized to accommodate future population growth of both villages and the surrounding areas and will act as a platform for social and economic development.

Infrastructure Delivery Lead, Seamus Glynn said: “We are delighted to announce the successful completion of this project which brings many benefits to the people of Baile Bhuirne and Baile Mhic Íre from an environmental, social and economic point of view.

The project will enhance the water quality by ending the discharge of poorly treated waste in the area. The new wastewater treatment plant will also accommodate housing and other potential developments in the surrounding areas for years to come.  

The completion of this project reflects Uisce Éireann’s commitment to the efficient delivery of critical infrastructure to support local communities. It is also another milestone in our €27 million investment into upgrading wastewater treatment in the Cork Mid-West area.

We would like to thank the local residents and businesses for their support and co-operation as we carried out this project.

 The project, which was delivered by EPS on behalf of Uisce Éireann, involved the construction of a new wastewater treatment plant, construction of an outfall pipe, upgrade works to the existing pumping station, a new rising main and decommissioning and demolition of the existing septic tank.

Uisce Éireann is on track to deliver a programme of unprecedented scale to stop the discharge of untreated or inadequately treated wastewater into our seas and rivers. 

Since 2014, Uisce Éireann has stopped approximately 50% of untreated wastewater that was being discharged to our rivers and the sea, with the completion of new wastewater treatment plants in 16 towns across the country.

Along with this project, Uisce Éireann is also progressing works on a number of new wastewater treatment plants in mid-West Cork, investing over €27 million in the construction of new wastewater infrastructure in Dripsey, Coachford and Inishannon. These projects will improve the wastewater treatment quality and capacity and ensure compliance with wastewater discharge regulations. These projects are expected to be completed by late 2021/early 2022.

Uisce Éireann is responsible for the delivery of all public water and wastewater services in Ireland. We are committed to continuously upgrading and developing critical infrastructure to support the growth needed in housing and across our economy, while protecting the environment and safeguarding water supplies.