Read what to do.

Burnfoot Water Mains Replacement

National Leakage Reduction Programme

Uisce Éireann, in partnership with Donegal County Council, has replaced ageing, problematic water mains in Inch Road, Burnfoot, Co. Donegal to provide a more reliable water supply and reduce high levels of leakage.

The works involved the replacement of approximately 1300 metres of aged problematic water mains with new modern pipes. The programme to replace the water mains on Inch Road, Co. Donegal commenced the start of June 2022. These works were carried out as part of Uisce Éireann’s National Leakage Reduction Programme.

The section of works took place along the L1861 and L1851 Inch Road, Burnfoot, Co. Donegal.

The works also involved laying new water service connections from the public water main in the road to customers’ property boundaries and connecting it to the customers’ water supply. Where the existing service connections on the public side are lead these were replaced as part of this improvement work.

The works were carried out on behalf of Uisce Éireann by Farrans Construction and were completed by mid-August 2022.

Location
Donegal
Status
Completed
Type
Leakage Reduction

What are the benefits of the works?

The benefits of the leakage reduction works include:

  • A Reliable Water Supply – Replacement of water mains and service connections will reduce the instances of bursts and water outages and will ensure a reliable supply of water to customers and local businesses in the area.
  • Reduced Leaks – Replacement of water mains and service connections will eliminate existing leaks and reduce the amount of clean drinking water lost into the ground.
  • Improved Operation and Maintenance – These works will deliver cost savings by providing improved water network operation that will require less maintenance in the future.

Will customers be affected by the works?

Areas of work will be limited to short sections to minimise impact on customers. Traffic management and temporary traffic lights will be in place during this time. Local and emergency traffic will always be maintained.

The works may involve some short-term water interruptions and the project team will ensure that customers are given a minimum of 48 hours’ notice prior to any planned water interruptions.

We understand that this type of work can be inconvenient and works crews will make every effort to minimise any disruption these necessary works cause.