Location
Carlow
Status
Completed
Type
Leakage Reduction

Benefits

A Reliable Water Supply

  • Replacing the old water mains with new water mains and service connections will reduce the instances of bursts and water outages and will ensure a reliable supply of water to customers in the area

Reduced Leaks

  • Replacement of old water mains and service connections in poor condition will eliminate existing leaks and reduce the amount of clean drinking water lost into the ground

Improved Water Quality

  • Removing existing old cast iron and lead from the water network and replacing them with new plastic pipes will reduce the risk of contamination

Improved Operation and Maintenance

  • These works will deliver cost savings by providing improved water network operation that will require less maintenance in the future

Steps

  • Works will involve the decommissioning and replacement of approximately 600 meters of old cast iron water mains on Tullow Street, Carlow
  • The existing mains will be replaced with high density polyethylene (plastic) pipes
  • The works will also involve laying new water service connections from the public water main in the road to customers’ property boundaries and connecting it to the customers’ water supply
  • The works are scheduled to commence on the 18 June and are expected to be completed by late August