Location
Tipperary
Status
Completed
Type
Wastewater

Benefits

  • Reduce the plant’s carbon footprint, which will equate to a 15 tonnes reduction in carbon emissions
  • Generate 32,000 kWh (kilowatt hours) per year of electricity, which will lead to a reduction in the demand for imported electricity at the site
  • Boost the resilience of the plant by ensuring a continuous supply of energy in the case of power outages
  • Reduce greenhouse gas emissions and increase energy efficiency at the plant

What is involved as part of this project?

  • Constructed 220 square metres of solar array in the southern part of the Nenagh plant, with this location selected to optimise the production of electricity
  • Installation of 128 photovoltaic (PV) solar panels to generate clean, renewable electricity for the plant
  • All construction works were undertaken within the boundary of the site, therefore minimising disruptions to residents and businesses of the surrounding area

View more projects