What are the benefits of this project?

  • Improved drinking water quality
  • Secure and safe water supply
  • Improved service levels

Details of ongoing works

Sheskinbeg:

  • Installation of 1.4km water main, transfer of service connections, temporary road reinstatement and decommissioning of the old main are now complete.

  • Road reinstatement currently in the settlement period and under review.

Argery, Ballindrait & Lifford:

  • Installation of 2.5km water main, transfer of service connections, temporary road reinstatement and decommissioning of the old main are now complete.
  • Road reinstatement currently in the settlement period and under review.

Derrybeg to Brinnalack:

  • Installation 5km water main, transfer of service connections, road reinstatement and decommissioning of the old main are now complete.
  • Road reinstatement currently in the settlement period, and under review.

Abbeylands, Ballyshannon:

  • Installation of 1.2km water main, transfer of service connections, road reinstatement and decommissioning of the old main are complete.
  • Road reinstatement currently in the settlement period, and under review.

Ballybofey South Backline (Cross Roads, Killygordon to Carrickmagrath, Ballybofey):

  • ​Installation of 9km water main, transfer of service connections, road reinstatement and decommissioning of the old main are complete.
  • Road reinstatement currently in the settlement period, and under review.

Corker, Rossnowlagh:

  • Installation of 4.1km water main, transfer of service connections, road reinstatement and decommissioning of the old main are complete.
  • Road reinstatement currently in the settlement period, and under review.

Ballyshannon Town:

  • Installation of the new water mains at Cluain Barrow, St Benildus Avenue and Erne Street commenced in September 2019.
  • Works will include decommissioning of the existing backyard water main at St Benildus Avenue and Erne Street and the installation of a new private side service connection to each property from the new water main.
  • It is expected that works will last for approximately 20 weeks.
  • Traffic management will be in operation during this period.

Three Trees, Inishowen:

  • Installation of 3.5km water main commenced on the R-238 in September 2019.
  • Works are scheduled to be completed by January 2020,
  • Traffic management will be in operation during this period.

Work Areas Commencing in 2019

Quigleys Point and Cabry:

  • Installation of 1.5km water main will begin on L-1951-1 at Quigley¡¦s Point and R238 at Cabry in November 2019.
  • It is expected that works will last for approximately 8 weeks.
  • Traffic management will be in operation during this period.

Bundoran West End:

  • Installation of 1.4km water main will begin on R-267 at Bundoran West End in November 2019.
  • It is expected that works will last for approximately 8 weeks.
  • Traffic management will be in operation during this period.

Completed Works

Carlin, Kerrykeel:

  • Installation of 2.4km water main, transfer of service connections, road reinstatement and the decommissioning of the old water main are now complete.

Doaghmore, Fanad:

  • Installation of 3.6km water main, transfer of service connections, road reinstatement and decommissioning of the old main are now complete.

Meenaleck to Rannafast:

  • Installation of 3.3km water main, transfer of service connections, road reinstatement and decommissioning of the old main are now complete.
     