What are the benefits of this project?

  • Improved drinking water quality
  • Secure and safe water supply
  • Improved service levels

Details of upcoming works

Carlin, Kerrykeel:

  • Installation of the 2.4km water main, transfer of service connections and the decommissioning of the old main are completed. Road reinstatement is ongoing.
  • Traffic management will be in operation during this period, diversion routes will be in place with local access maintained,
  • Works are scheduled to be complete by the end January 2019.

Doaghmore, Fanad:

  • Installation of the 3.6km water main is completed. Transfer of service connections, road reinstatement and decommissioning of the old main is ongoing.
  • Traffic management will be in operation during this period, diversion routes will be in place with local access maintained.
  • Works are scheduled to be complete by the end of January 2019.

Meenaleck to Ranafast:

  • Installation of the 3.3km water main and transfer of service connections are completed. Road reinstatement and decommissioning of the old main is ongoing,
  • Traffic management will be in operation during this period, diversion routes will be in place with local access maintained,
  • Works are scheduled to be complete by the end of January 2019.

Argery, Ballindrait & Lifford:

  • Installation of the 2.5km water main commenced at Argery in mid December 2018. It is expected that works will last for approximately 12 weeks.
  • Traffic management will be in operation during this period, diversion routes will be in place with local access maintained.

Work Areas Commencing in 2019:

Sheskinbeg:

  • Installation of the 1.4km water main will begin on L-1263 at Stranacorkragh in January 2019. It is expected that works will last for approximately 5 weeks.
  • Traffic management will be in operation during this period, diversion routes will be in place with local access maintained.

Derrybeg to Brinnalack:

  • Installation of the 5km water main will begin on R-257 at Derrybeg in February 2019. It is expected that works will last for approximately 20 weeks.
  • Traffic management will be in operation during this period.

Ballybofey South Backline (Cross Roads, Killygordon to Carrickmagrath, Ballybofey):

  • Installation of the 9km water main will begin on L-3044-6 at The Cross, Killygordon commencing in mid January 2019 and progress towards Carrickmagrath, Ballybofey. It is expected that works will last for approximately 26 weeks.
  • Traffic management will be in operation during this period.

Remaining Work Areas:

Remaining schemes currently at design stage. Further details to be provided once available. Anticipated commencement dates outlined below:

Scheme LocationAnticipated Commencement Date*
Three Trees, Quigleys Point April 2019
Corker, Ballyshannon April 2019
Bundoran, West End April 2019
Ballyshannon Town June 2019
Abbeylands, Ballyshannon July 2019
Cabry, Redcastle July 2019

 