Location
Dublin
Status
In Progress
Investment
€21.7 million

News and Updates

Two week look-ahead for upcoming works in Malahide and Swords

Location Proposed Dates Duration Planned Works Traffic Management
Swords/Malahide Road 6 - 17 July 10 days Trial holing & road reinstatement Shuttle Stop and Go System  - Attached below
Malahide 6 - 17 July - No works planned N/A

Traffic Management

  • VMS Signage will be installed in Swords on the Malahide Road to advise motorists and stakeholders of the works.
  • Shuttle Stop and Go Traffic Management and Road Narrows will be in place for these works
  • Advanced traffic management warning signage will be in place and shared to AA Road Watch.
  • Working areas will be kept to a minimum to minimise traffic congestion.
  • Local and emergency access will be maintained at all times.

Stakeholder Engagement

These works will be carried out in phases and limited to short sections to reduce impact to businesses and residents. All residents and businesses have been communicated with in relation to the works. Local access will be maintained at all times.

Progress

Malahide – There are no works scheduled in Malahide between 06 July to 17 July 2020. Works have progressed along the Back Road/The Hill Junction/Seamount Road/Seamount Drive with traffic flow moving well with the shuttle system in operation.

Swords - Site investigation and road reinstatement works are scheduled to commence in Swords on the Malahide Road on 06 July 2020. The project team will endeavour to keep you updated as the project progresses.

Location 1 Phase 1: Swords/Malahide Road - Traffic Management

Location 1 Phase 2: Swords/Malahide Road - Traffic Management

Location 2: Swords/Malahide Road - Traffic Management

Location 3: Swords/Malahide Road - Traffic Management

Location 4: Swords/Malahide Road - Traffic Management

Location 5: Swords/Malahide Road - Traffic Management

What is involved?

  • As part of this project, Irish Water will construct approximately 2.5 kilometres of water main between Swords and the Seamount Reservoir in Malahide.

Benefits

  • Improve the security of the drinking water supply.
  • Safeguard the water supply to this area.

What are the next steps?

It is planned that works will commence in Malahide in early March 2020. Works will involve the upgrading of water mains on:

  • The Back Road
  • The Bawn Grove
  • Castlefield Manor Entrance
  • R124, The Hill
  • Seamount Road
  • Seamount Drive
  • Swords/Malahide Road

The Project Team will endeavour to keep you updated as the project progresses.