Location
Clare
Status
Planned
Investment
€1.8 million

Benefits

  • Upgrade existing infrastructure at the plants and provide new elements where defects identified
  • Improve the performance of the wastewater treatment process
  • Prolong the operational life of the existing plants
  • Reduce the risk of storm water flooding
  • Ensure compliance with Urban Wastewater Treatment Regulations 2001

Steps

  • Construct a new inlet works and a new 1,000m3 storm water tank at the Clareabbey plant
  • Construct and install a 50m³ storm water holding tank and a sludge holding tank at the Inagh plant
  • Works will be carried out within the footprint of the plants, therefore minimising disruption to residents and businesses in the surrounding area